What is the test date for a test that is started and finished on different days?

Document created by Community User on Jul 29, 2016Last modified by Community User on Jun 6, 2017
Version 8Show Document
  • View in full screen mode
Question
When a test has been started and completed on different days, which date is recorded as the test date?

Answer
The start date of a completed test determines the test date on reports. For example, if a student begins a test on May 10 and completes the test on May 20, the test date for reporting purposes is May 10. The test should appear on reports if the test window includes May 10, and all other properties of the test are valid.